Project Timeline

 

October 2014 Building areas decommissioned and blessed by Ngāti Whātua o Ōrakei
November 2014 Cunningham Building renovations scheduled to begin
July 2015 Cunningham Building complete and Hamilton Building works scheduled to begin 
June 2016 Hamilton Level 6 complete 
December 2016 Hamilton Level 5 complete
June 2017 Hamilton Level 4 complete
September 2017 Hamilton Level 3 complete
February 2018 Hamilton Level 2 complete
February 2018 Hamilton Level 1 complete 
April 2018 Project complete